By Andrea McDowell (
amcdowell@ortech.ca ) Reading time: 2 minutes 30 seconds
Given the focus put on Natural Heritage and Public Consultation in
the Class EA and REA processes, it’s easy to let the archaeological and
cultural heritage assessments slide. This can be dangerous, as weather
restrictions are every bit as real for archaeology as for natural
heritage; it’s easy for a last-minute change to a layout to derail a
project if the archaeological study has not been properly planned.
Following are a few things to keep in mind:
1. Plan on snow
It’s
tempting to hope for good weather and plan your archaeological field
surveys later in the fall or earlier in spring, but if Mother Nature has
a long winter in mind, you could find your work and your project
delayed by a season or three. Fields not only need to be clear of snow
and crops, they need to be recently ploughed and weathered for at least a
few weeks. Give yourself enough time to get the project location
ploughed and weathered well before there is a chance of snow in the
fall, or you could be waiting until April or May to get the field work
done.
2. Plan on layout changes
No matter
how final your layout is today, there is always the possibility that it
will be less final tomorrow. New noise receptors, new natural heritage
information, new agency guidelines, new turbine model specs,
geotechnical studies, and newly endangered species all have a way of
shifting final turbine locations and roads by a few to a few hundred
metres when you can least afford new field studies. Try to give yourself
the space to move project components later when you need to by
surveying a much larger area than you plan to use. If the budget allows
it, you may want to consider having entire usable fields surveyed, as a
single pass at the beginning over a large area is much less expensive
than multiple smaller passes later on when project components shift.
3. Plan on agency delays
Archaeological
studies can take several months to review, revise, and receive
confirmation letters for. Anticipate at least seven months between the
submission of the report and receipt of the MTCS sign-off.
4. Plan on a cultural heritage study
It’s
tempting to push back against the requirement for a cultural heritage
study, particularly if you are in a relatively undeveloped area with few
apparent cultural heritage resources. However, cultural heritage
studies typically cost less than $10,000, can be completed in a few
weeks at any time of year, and take less time for agency review than
archaeological studies do. They are typically the least troublesome part
of any energy project approval application. Unless your project truly
cannot afford the six weeks from contract signature to MTCS confirmation
letter, consider completing the cultural heritage study before the MTCS
requests it.