By Andrea McDowell (
amcdowell@ortech.ca ) Reading time: 3 minutes 30 seconds
Environmental field work in support of an environmental assessment
forms the bulk of the work required to gain regulatory approvals and
permits for a new energy project. It’s also unpredictable, depending on
factors such as terrain, results of preliminary field studies,
ever-changing regulations and guidelines, and weather conditions. But
take heart: there are steps that can be taken in the project planning
stages to minimize delays and maximize the chance that your approvals
will be received on time.
1. Complete a thorough constraints study before beginning
Different
kinds of habitats require different kinds of field studies at different
times of year. Doing legwork to understand what features might be
possible at your project site will allow you to work those restrictions
into your schedule from the outset. While surprises can always arise
later when biologists are on the ground—an endangered species found
during botanical surveys, a sighting of a rare bird—a detailed
constraints analysis will allow you to rule out many features in
advance.
2. Gain (or hire) a thorough understanding of all of the Natural Heritage Assessment guidelines in Ontario
Regulations
can be misleading when it comes to Natural Heritage Assessments. The
Renewable Energy Approvals regulation, for instance, states only that a
“site investigation” must be done of all lands and waters within 120m of
a planned project location. It would be easy to assume that detailed
notes from a site investigation taking a single day would meet the
requirement of the regulation. However, the Ministry of Natural
Resources must be satisfied that the investigation conforms to their
guidelines and protocols; and manuals detailing those guidelines and
protocols run for thousands of printed pages.
The details buried in
those printed pages can make or break your project schedule. It is
imperative that whoever is planning your Natural Heritage work know what
studies need to be done at what time of the year; if you don’t get your
amphibian surveys underway by March or April, depending on where in the
province you are, you will be waiting until next March or April to
begin. Similarly, many studies can only be conducted under certain
weather conditions—light or dark, above 8C or 20C, sunny or cloudy.
3. Use pre-construction survey commitments to your advantage wherever possible
In
some cases, it is possible to defer certain kinds of habitat usage
surveys until after completion of the Environmental Assessment
documents, if the habitat is treated as significant in the reports with
all appropriate mitigation measures factored in. If the habitat turns
out to be significant when later evaluated, the appropriate protections
are already in place; if it’s not, those mitigation measures and other
commitments no longer apply.
This process is well-developed with
Renewable Energy Approval studies, but it is also worth trying with
other EAs where waiting for the appropriate time for necessary studies
may put a project at risk. This will depend on negotiations between the
Ministry of Natural Resources and the biologists who will be undertaking
the field studies.
4. Beware turnover
Some government agencies
have high rates of turnover thanks to a dependence on short-term
contract staff. The regulator you are dealing with today may no longer
be around when the reports are submitted for final approval. While it is
tempting to accept if a regulator offers to cut you some slack on the
timing restrictions of a particular study or the specific work involved,
keep in mind that the final decision-maker may have a different
perspective; if you end up needing to re-do some portion of your
program, it can end up being more expensive and time-consuming than if
you’d gone the long way around to start with. Know how much risk you are
willing to assume with turnover rates at the agency you are dealing
with, and add some buffer to your schedule in case you need to repeat a
portion of your field work.
Natural Heritage Assessments and the
associated field investigations can represent 80% of the effort and time
required to complete and environmental assessment—a situation often
frustrating for project proponents and designers, who are used to the
more structured and predictable worlds of engineering. However, the
risks and uncertainties—if accepted and planned for from the outset—can
be successfully managed, allowing your project to be constructed on
time.